On Mon, Oct 15, 2012 at 6:35 AM, Stephan Kulow
Hi,
I played with dates and holidays and it's *very*, *very* tight ;(
What I came up with is basically:
20121003: Milestone 0 20121108: Milestone 1 20121213: Milestone 2 It's 5 weeks between 1 and 2, but releasing one in between is not worth it and I can make 1 earlier and 2 later ;( 20130117: Beta1 20130207: RC1 20130228: RC2 20130307: GM 20130313: FCS
In theory this can work out, but in practice we again have gained 94 packages not building ;(
Greetings, Stephan
Very, very tight with a community project like this makes me nervous. sysvinit removal is still part of that as far as I know. I'd still vote for a respin to be released sometime in the winter (jan-mar) with the latest kde/gnome and then release 12.3 in July. (A 4 month delay). Greg -- To unsubscribe, e-mail: opensuse-factory+unsubscribe@opensuse.org To contact the owner, e-mail: opensuse-factory+owner@opensuse.org