15 октября 2012 12:35:23 Stephan Kulow написал(а):
Hi,
I played with dates and holidays and it's *very*, *very* tight ;(
What I came up with is basically:
20121003: Milestone 0 20121108: Milestone 1 20121213: Milestone 2 It's 5 weeks between 1 and 2, but releasing one in between is not worth it and I can make 1 earlier and 2 later ;( 20130117: Beta1 20130207: RC1 20130228: RC2 20130307: GM 20130313: FCS
In theory this can work out, but in practice we again have gained 94 packages not building ;(
Greetings, Stephan
Adding new packages to factory is possible up to Beta1 or Milestone 2? I'm going to add most part of packages from science repository to factory. -- To unsubscribe, e-mail: opensuse-factory+unsubscribe@opensuse.org To contact the owner, e-mail: opensuse-factory+owner@opensuse.org