On 21/03/2016 12:14, Ludwig Nussel wrote:
Hi,
Time flies, so let's start planning the schedule for Leap 42.2. The current version 42.1 is based on SLE12 SP1 and 42.2 is meant to be based on SP2¹. SLE12 SP2 is expected to reach the beta phase mid of May which means we'll get the package sources in OBS then. That in turn will allow us to start building Leap on top.
My plan would be to have a first Alpha end of May based on 42.1 sources with the SLE bits updated to SP2. The next snapshot should be before OSC in June and another one in July. I'd aim for the the first Beta last week of August, followed by Beta2 around September 21st. RC1 would then be Oct 6, followed by RC2 Oct 18. GM Oct 27 so we can release November 2nd.
cu Ludwig