Hi, I played with dates and holidays and it's *very*, *very* tight ;( What I came up with is basically: 20121003: Milestone 0 20121108: Milestone 1 20121213: Milestone 2 It's 5 weeks between 1 and 2, but releasing one in between is not worth it and I can make 1 earlier and 2 later ;( 20130117: Beta1 20130207: RC1 20130228: RC2 20130307: GM 20130313: FCS In theory this can work out, but in practice we again have gained 94 packages not building ;( Greetings, Stephan -- To unsubscribe, e-mail: opensuse-factory+unsubscribe@opensuse.org To contact the owner, e-mail: opensuse-factory+owner@opensuse.org